TotalEnergies Cancels $16 Billion Green Hydrogen Plant in Chile

TotalEnergies has cancelled its $16 billion green hydrogen and ammonia project in Chile's Magallanes region, citing high costs and insufficient long-term demand for 'green molecules'.

By James Calloway3 min read566 words

In brief

  1. TotalEnergies cancelled a $16 billion (£12 billion) green hydrogen and ammonia plant in Magallanes, southern Chile.
  2. The project planned up to 1.9 million tonnes of annual capacity on a 72,000-hectare site, requiring up to 2GW of electrolysis.
  3. The company called the investment 'economically unfeasible', citing insufficient demand for long-term offtake.
  4. Chile's Corfo had promoted domestic hydrogen-based fertilisers as a shield against geopolitical supply shocks.
Huge green hydrogen project scrapped due to “high costs”
Huge green hydrogen project scrapped due to “high costs” — ClickerHappy / pixabay

TotalEnergies has scrapped a $16 billion (£12 billion) green hydrogen and ammonia plant in southern Chile, calling the investment "economically unfeasible" in a formal withdrawal request first reported by gasworld.

The numbers behind this project were big. Now they are simply gone. The plant was planned for a 72,000-hectare site in the Magallanes region, at the southern tip of Chile, with a predicted annual capacity of up to 1.9 million tonnes of hydrogen and ammonia. Producing that volume would have required up to 2GW of electrolysis capacity — electrolysis being the electricity-hungry process that splits water into hydrogen and oxygen.

Why did TotalEnergies pull out?

The company blamed two things: high costs and demand that never showed up.

In its withdrawal request, TotalEnergies said it had already incurred "significant development expenses" before concluding that demand for green molecules remains insufficient to secure long-term offtake — that is, committed buyers — on economically viable terms. Translation: nobody was lining up to purchase the output at a price that would pay back a $16 billion bet.

That is a sobering admission, and worth dwelling on. The project was not killed by bad geology or missing permits. It died because the customers are not there yet, even in one of the best places on Earth to make the stuff.

Chile, after all, has what most countries envy: enormous low-cost renewable energy potential, particularly wind in the far south. If green hydrogen cannot pencil out there, sceptics will reasonably ask where it can. The cancellation sits awkwardly alongside years of industry optimism about Chile as a future hydrogen export powerhouse.

What about the government's case?

There was a policy argument, too, and it has now lost its flagship private backer. Corfo, the Chilean government's economic development agency, had suggested that domestically produced hydrogen-based fertilisers could ease supply problems caused by global geopolitical events. The logic is straightforward: make fertiliser inputs at home, and you are less exposed to international shocks.

With TotalEnergies out, that argument remains just that — an argument. No plant, no domestic fertiliser supply chain. Corfo has not, according to the available reporting, named a replacement developer, and we do not know whether other firms are waiting in the wings.

What does this change for green hydrogen?

For the industry, the honest answer is: a warning shot, not a death blow. One cancelled project does not kill a technology, but a $16 billion cancellation by a multinational major does signal that bankability — the ability to finance a project against real customer commitments — remains the sector's weak point.

For Chile, it means a flagship megaproject in Magallanes will not materialise, along with whatever construction jobs and regional investment it implied. The reported details do not include figures for expected employment, so any claim of specific job losses would be speculation.

The usual caveats apply. We are working from a withdrawal request and early reporting, not a post-mortem. Costs, demand forecasts and the exact tipping point for the decision are not laid out publicly. Other projects in Chile and elsewhere are proceeding.

Still, the core lesson is hard to dodge. Cheap renewable electricity is necessary for green hydrogen, but it is not sufficient. Without buyers willing to sign long-term contracts at viable prices, even the sunniest and windiest corners of the planet will struggle to turn hydrogen hope into hydrogen hardware.

via energylivenews.com (Source)

Filed under

  • green-hydrogen
  • ammonia-production
  • electrolysis
  • renewable-energy
  • chile
Share this article:

More from James Calloway

James Calloway

Show full bio

Staff writer covering regulation, policy and their impact on general science news at SciBeat.

584 articles

Nearby plates

« Previous articleNext article »