Second U.S. nationwide ground stop since 9/11 exposes network risks
A Friday telecommunications failure triggered the second U.S. nationwide ground stop since 9/11. Congress allocated $12.5 billion for an FAA modernization phase with more than 11,000 projects.
By Nathan Brooks5 min read908 words
In brief
- A Friday telecommunications failure led to the second nationwide U.S. ground stop since 9/11.
- Congress allocated $12.5 billion last year for air traffic control upgrades.
- The first modernization phase includes more than 11,000 distinct projects without an integrated master plan.
- The legacy telephone network dates to the 1980s and is being converted from copper wiring to fiber-optic cable.
- The September GAO report warned that faster timelines bring cost uncertainty and airspace disruption risks.

A Friday telecommunications failure triggered a nationwide U.S. ground stop, a broad hold on departures, canceling Rossana D’Antonio’s flight and thousands of others. It was the second such stop since 9/11. The FAA said the incident began with router installation at a remote Arkansas facility, but the agency still could not explain the full cause.
D’Antonio was about to board at John F. Kennedy International Airport in New York, bound for Los Angeles, when the FAA halted flights nationwide. The frequent flier got a seat Saturday morning, only to find hotels booked; she spent Friday night at JFK.
She is also president-elect of the American Society of Civil Engineers. She immediately focused on infrastructure, arguing that engineers had warned the system was state of the art in the 1980s. Her conclusion was that the country had long known about the aging network and had failed to act quickly enough.
Why does the FAA still rely on 1980s technology?
Federal Aviation Administration head Bryan Bedford described the dependency on Thursday at Honeywell Aerospace’s American Aviation Leadership Summit in Washington. He called it “a patchwork, archaic federal telephone network.” Bedford said the agency needed to leave that network as quickly as possible while maintaining safety.
No one disputes that the old equipment is a problem, and current modernization should have begun years ago. The replacement work swaps outdated copper electrical cables for fiber-optic lines, which carry data as pulses of light. Connecting that fiber-designed equipment with the legacy network remains difficult.
Former FAA and Department of Transportation officials trace the delay to decades of underfunding. Michael Huerta, a former FAA administrator during the Obama administration, said the core issue was money: the agency had been asked to do more with less.
The FAA tried to invest in new technology, but the older systems must keep aircraft flying 365 days a year, 24 hours a day. Those obsolete networks are fragile and costly to maintain, and they resist links with equipment designed for fiber. As a result, the world’s busiest and most complex airspace still depends on network technology from the 1980s.
Former FAA executive William Voss, who worked on modernization efforts in the 1990s, said the work should have started earlier. He compared the legacy setup to an antique store in the biggest air traffic system in the world, where keeping the old operation running consumed the money available for change. Voss said that burden helps explain why the agency now faces a daunting task.
Why is the modernization schedule drawing criticism?
Congress allocated $12.5 billion last year to upgrade the air traffic control system. Voss described the work as complicated and daunting because few organizations have completed a transformation of that scale in one large leap. He warned that the Trump administration was moving too quickly, without enough time for planning and coordination.
Voss also questioned why the failed network upgrade had been scheduled on a busy Friday afternoon. In his view, that timing suggested the agency was under tremendous schedule pressure. Dave Spero, national president of Professional Aviation Safety Specialists, a union representing FAA technicians, said he would not attempt that installation then.
For safety, Spero said, he would probably schedule the work during a midnight shift. The Government Accountability Office echoed the scheduling concern in a report published in September, saying the administration was accelerating modernization already underway. That acceleration included the telecommunications network that failed on Friday.
Kevin Walsh, director of the GAO’s Information Technology and Cybersecurity team and lead author of the report, said: “They are basically buying speed at the risk of cost uncertainty and the potential for disruptions in the national airspace.” His team also said the first modernization phase contains more than 11,000 distinct projects without an integrated master plan.
An integrated master plan is a coordinated schedule that ties individual projects together. The GAO said that approach might work, but it increases outage risk, meaning interruptions in service, especially because older systems are already prone to failure. More speed can therefore mean more uncertainty in both cost and service.
Is the administration moving too quickly?
The Trump administration defended its approach. After meeting Republican senators at the Capitol on Tuesday, Transportation Secretary Sean Duffy compared the pace with Goldilocks’ choice between being too fast and too slow. He argued that the longer the FAA remains on the old, rickety network, the less safe it becomes.
Eric Soskin, a former Department of Transportation inspector general, offered another reason for the push. Decades of modernization attempts took longer and delivered less than promised, he said, so the FAA wants to show Congress it will finish this effort. Soskin called that commitment a powerful signal that an important project would now be carried out.
Can the FAA prevent another major disruption?
The FAA still has substantial modernization work ahead, and former agency leaders see a risk of more disruptions. Michael O’Donnell, a former senior FAA executive, said he did not expect another major U.S. airspace shutdown because the agency would avoid one at all costs.
He expects some disruption, but not on Friday’s scale. He said another event of that size would shock, surprise and worry him.
For now, the FAA must keep the legacy network running while it advances the modernization. The unexplained failure leaves both operational and planning risks as the $12.5 billion effort advances.
via feeds.npr.org (Source)
More from Nathan Brooks
Show full bio
Market editor covering companies, deals and strategy in general science news at SciBeat.
563 articles
Nearby plates
- FAA Ground Stop Spurs $50 Billion Push for Congress Funding
- Every U.S. Flight Grounded Three Days After Nationwide AI Traffic Rollout
- NASA Greenlights New Boeing Starliner Missions After Troubled Test Flight
- 63% of Remote First Nations Homes Lack Working Free-to-Air TV
- Mariner 9 Became the First Craft to Orbit Another Planet on Nov. 13, 1971